The programme of landscape revitalization and integrated river basin management in the Slovak republic for the year 2011 - retention measures in the Sobotište village. [斯洛伐克]

Program revitalizácie krajiny a integrovaného manažmentu povodí v Slovenskej republike pre rok 2011 - vodozádržné opatrenia v obci Sobotište. (Slovak language)

approaches_2680 - 斯洛伐克

完整性: 72%

1. 一般信息

1.2 参与方法评估和文件编制的资源人员和机构的联系方式

关键资源人员

SLM专业人员:
有助于对方法进行记录/评估的项目名称(如相关)
Sustainable Hill Cultivation Programme

1.3 关于使用通过WOCAT记录的数据的条件

(现场)数据是什么时候汇编的?:

01/01/2015

编制者和关键资源人员接受有关使用通过WOCAT记录数据的条件。:

1.4 SLM技术问卷的参考

Level ditches in cropland
technologies

Level ditches in cropland [斯洛伐克]

Conservation measures for eroded cropland. The technology contains level ditches of various lengths, which are digged along a contour.

  • 编制者: Zuzana Studvova
Wooden check dams
technologies

Wooden check dams [斯洛伐克]

Small wooden check dams built in erosion rills, grooves or gorges to reduce flood risk.

  • 编制者: Zuzana Studvova

2. SLM方法的描述

2.1 该方法的简要说明

This approach is devoted to the implementation of 'The Landscape Revitalisation Programme and integrated river basins management of the Slovak Republic' in the Sobotište village.

2.2 该方法的详细说明

该方法的详细说明:

Aims / objectives: The objective of the first implementation project for 2011 was to create, activate and systematically implement a minimum of 6 million m³ of water retention elements in mountain and foothill areas of forest-agricultural landscape in Slovakia. A particular aim was to create and build landscape water retention systems, terrain elements, facilities and technical solutions in forest, agricultural and urban areas in selected village locations, with the abovementioned cyclical rainwater retention capacity, which will then be operated and
maintained. Another project objective was to force and socially support the creation of employment at community and regional level. The creation of water retention elements and the implementation of revitalisation measures required the creation of a minimum of 2,500 jobs of a seasonal and temporary nature in 2011, including extending existing specialist capacities. This whould also extend the work skills and knowledge necessary for revitalisation of the landscape.
833 municipalities showed interest to participate in this project/approach, while 200 municipalities met the criteria. The project created about 3,500 seasonal jobs in 2011, particularly in regions with high unemployment.


Methods: Criteria and their significance for including villages into the first implementation project are
as follows:
1. 45% - historic or regularly repeated occurrence of flash flooding,
2. 35 % - village is situated in a location with a high potential risk of flooding, in accordance
with modelled potential for the occurrence of flooding. A map of regional and local
potential for flooding in the area of Slovakia1
is at Appendix No. 1,
3. 10% - location of a village in the upper part of river basins, so the implemented measures
will positively decrease the risk of flooding for highest possible number of villages in the
given river basins,
4. 10% - the ratio of documented unemployment is taking into account so citizens of villages
with a high ratio of documented unemployment could contribute towards revitalisation
works.

The submitted methodology of the whole flood potential of Slovakia was prepared on the basis of the work of J. Minár and Co. (2005). The mentioned work focuses upon the
presentation of methodology and results for evaluating the flood creation potential within the whole of Slovakia. It also includes a general description of the modelling of hydrological
processes. The method presented in this work is a good alternative for fast, effective and relatively financially undemanding but still sufficiently reliable analysis of flood risks of
larger areas. The actual calculation of total potential for flooding took place in the technological environment of Geographic Information Systems (GIS) in the following steps
with the stated data:

- calculation of the morphometric potential (incline, horizontal articulation of the
topography, slope length, speed of surface run-off),
- partial synthetic geological potential (infiltration and drainage properties of the soil,
retention properties of the land cover, breaking effect of land cover, size of river basin,
shape of river basin),
- overall potential of the land for the creation of flood situations (climatic and
hydrological characteristics and data).

Stages of implementation: Management of the first implementation project was carried out by the Executive Manager of the Programme of Landscape Revitalization and Integrated River Basin Management in SR in cooperation with the Government Representative for Local Government and for Integrated River Basin and Landscape Management and other interested departments of the Government Office SR.

2.3 该方法的照片

2.5 采用该方法的国家/地区/地点

国家:

斯洛伐克

区域/州/省:

Slovakia

有关地点的进一步说明:

Senica / Sobotište

2.6 该方法的开始和终止日期

注明开始年份:

2011

终止年份(若不再采用该方法):

2012

2.7 方法的类型

  • 基于项目/方案

2.8 该方法的主要目的/目标

The Approach focused mainly on SLM with other activities

The Sobotište of village was greatly affected in 2011 by floods from storm rainfall. Problems with floods, however, occur regularly, especially at the Teplica and the Sobotišský stream. Some problems have been recorded in farmland and meadows, in places of concentrated runoff during the storm rainfalls, long lasting rainfalls, and snow melting. Floods endanger villages and make severe damage. The goal of the approach is to eliminate damage to healt and properties.

Water retention measures are proposed in the territory of Sobotište, localities of Kubiny, Staré Hory, Javorec, Kaničkov Jarok and Padelky. It is expected that the proposed water retention measures will support the accumulation and infiltration of water into the soil and retard runoff from farmland, meadows, and pastures. With the proper function of measures the surface runoff in farmland will decrease and slow down, and community will not endanger as much as previously.

The SLM Approach addressed the following problems: In general, the main problems within the implementation of projects are mostly legislative regulations that hamper the SLM and the implementation of technologies. The big problem is protection zone of particular rivers connected to administrative and legislative laws and regulations. Some difficulties detected were the execution of permissions for the implementations of methods and technologies that would help to achieve the sustainable land management.
Second problem is land consolidation. The process of the land consolidation is too long to be achieved and accomplished in time. Especially if the public call of the application submission for subsidies needs the consolidation of land to be already solved.
Third, the measures cannot be more expensive than the protected object.
Four, there is lack of money for the purchasing the land in municipalities.
Five, there is very poor law enforcement and recovery of law and claims.

2.9 推动或妨碍实施本办法所适用的技术的条件

财务资源和服务的可用性/可得性
  • 阻碍


Treatment through the SLM Approach:

法律框架(土地使用权、土地和水使用权)
  • 阻碍

ownership of the land

Treatment through the SLM Approach:

3. 相关利益相关者的参与和角色

3.1 该方法涉及的利益相关者及其职责

  • 当地土地使用者/当地社区

The approach involved socially and economically disadvantaged ethnicities

  • SLM专家/农业顾问
  • 国家政府(规划者、决策者)
3.2 当地土地使用者/当地社区参与该方法的不同阶段
当地土地使用者/当地社区的参与 指定参与人员并描述活动
启动/动机 自我动员 Government
计划 自我动员 Government, SLM specialist
实施 自我动员 Municipalities, land users
监测/评估 自我动员 Municipalities, land users
Research 被动

3.4 有关SLM技术选择的决策

具体说明谁有权决定选择要实施的技术:
  • 主要是土地使用者,由SLM专家提供支持
解释:

Decisions on the method of implementing the SLM Technology were made by mainly by land users supported by SLM specialists

4. 技术支持、能力建设和知识管理

4.1 能力建设/培训

是否为土地使用者/其他利益相关者提供培训?:

4.2 咨询服务

土地使用者有权使用咨询服务吗?:

4.3 机构强化(组织发展)

是否通过这种方法建立或加强了机构?:

4.4 监测和评估

监测和评估是该方法的一部分吗?:

4.5 研究

研究是该方法的一部分吗?

明确话题:
  • 技术
提供进一步的细节,并指出是谁做的研究:

Research was carried out on-farm

5. 融资和外部物质支持

5.1 该方法中SLM组成部分的年度预算

如果不知道准确的年度预算,请给出一个范围:
  • 10,000-100,000
注释(例如主要的资助来源/主要捐助者):

Approach costs were met by the following donors: government: 100.0%

5.2 为土地使用者提供财政/物质支援

土地使用者是否获得实施该技术的财政/物质支持?:

如果是,请具体说明支持的类型、条件和提供者:

Government funds and subsidies

5.3 对特定投入的补贴(包括劳动力)

  • 设备
具体说明哪些投入得到了补贴 程度如何 对补贴做出具体说明
机械 充分融资
工具 充分融资
  • 农业
具体说明哪些投入得到了补贴 程度如何 对补贴做出具体说明
种子 充分融资
化肥 充分融资
  • 建筑
具体说明哪些投入得到了补贴 程度如何 对补贴做出具体说明
石料 充分融资
木材 充分融资

5.4 信用

是否根据SLM活动的方法给予信用值?:

7. 参考和链接

7.1 方法/信息来源

  • 实地考察、实地调查
  • 与土地使用者的访谈

模块